Update Progress Desain Ruko 5 x 15 meter - 2 Lantai
B. Tampak Depan
|
Daftar Gambar/Item |
|
Progress |
Keterangan |
|
A. RAB |
|
0% |
|
|
B. Gambar 3D exterior |
|
50% |
Konsep Sketsa |
|
C. Gambar Layout / Denah Tata Ruang |
|
100% |
Draft |
|
D. Gambar (2D) : - Gambar tampak depan - Gambar tampak samping kanan |
❌ ❌ |
0% 0% |
|
|
E. Gambar Potongan
: - Pot melintang A - Pot memanjang B |
|
0% 0% |
|
|
F. Gambar Rencana
meliputi : - Rencana Pondasi - Rencan Sloof - Rencana Kolom - Rencana Ringbalok
- Rencana Pintu - Rencana Jendela - Rencana Atap - Rencana Titik
Lampu - Rencana Instalasi
Listrik - Rencana Air
Bersih - Rencana Air Kotor
- Rencana Air
Buangan - Rencana Air Hujan |
❌ ❌ ❌ ❌ ❌ ❌ ❌ ❌ ❌ ❌ ❌ |
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% |
|
|
G. Gambar Detail meliputi : - Detail Pondasi - Detail Sloof,
Kolom, & Ringbalk, plat Lantai - Detail Kusen
Pintu & jendela - Detail Tangga - Detail Fasad ( Pilar, Dak Beton, Profil, dll ) / detail partial & typical |
❌ ❌ ❌ ❌ ❌ |
0% 0%
0% 0% 0% |
|